Wednesday, July 16, 2008

July 16, 2008, Site Meeting

Scott with K&A reported that he expects to hand the building over to Doug by August 1. This leaves two weeks worth of work to get the building completed so that Doug can begin moving in and training employees. Doug expects to have a soft opening on August 7. The wires for the flat panel t.v. has been pulled throught the existing conduit. You can see how big the cables were in the last picture just right of center. Scott said that axle grease did the trick. This saved a lot of time and money verses replacing all the conduit with larger conduit. The following issues were discussed:
  • Electrical hook up for cooler
  • Right patio exit steps
  • Question was raised about patio gates being set up for emergency exit.
  • Painting progress
  • Need to find contractor to who can apply finish to bar top.

Patio area. The railing is painted with final color. Two more coats will be applied.


View of side and right front of building.


Front entrance.


Rear view.

The block inside has a primer coat on it. The red section above the bar is the same color as the final block color. sheet rock will soon be primed and painted.