Thursday, February 14, 2008

February 13, 2008

The meeting was moved to Evans' office because of the below freezing tempature. However, the work continued on. All the dirt from under the building pad has been removed and the new dirt has been put in place. The old dirt was removed down to 6 feet under the building pad area. The new dirt is a light brown color in the pictures. The rest of the lot has been lowered and gravel has been put down. All this has been done since last Thursday. Visually, the progress seemed to be the greatest this past week as compared to earlier weeks. The other pictures below show the retaining wall footing being dug. You can also get an idea of how much the lot was brought down on the north side, west side and the northwest corner.