This picture shows the sheet rock above the block. The block will be painted red and the sheet rock above will be a tan color.Wednesday, June 11, 2008
June 11, 2008, Site Meeting
It has been several weeks since I was at the site and almost a month since I have updated the blog. I did not take pictures at the last site visit. As you can tell, the project has come along dramatically in the last month. The building is starting to really come together. The roof is complete enough for the drywall to be hung and finished inside the building. You will also notice all the conduit, duct, and sprinkler system pipe that has been run along the ceiling. The outside is looking good as well. The brick work has almost been completed. The windows will be installed as soon as the brick work is done. You will also not the dryvit work just under the roof over hang. This is going to add a nice touch to the outside finish.
This picture shows the sheet rock above the block. The block will be painted red and the sheet rock above will be a tan color.
This picture shows the sheet rock above the block. The block will be painted red and the sheet rock above will be a tan color.Thursday, May 8, 2008
May 7, 2008 Site Meeting
The major progress this week includes: electrical rough in, metal studs on exterior, mechanical rough in, roof framing, and exterior drywall. The major development is the power pole on the side street that had to be moved. The pole was determined to be too close to the building and roof over hang.
Roof frame work.
April 30, 2008 Site Meeting
Wednesday, April 16, 2008
April 16, Site Meeting
The Houndstooth is starting to come together nicely. The brick work has begun. You will notice the accent brick with the rough surface every seventh course on the way up the side of the building. This will break up the look of the brick nicely. The roof joists have also arrived. In the pictures below, you will see the crane setting the roof joists in place. These pieces will be welded to the steel structure. This will allow the roof work to progress in a timely manner. The block has been damp proofed on the outside of the building. The black color is from the application of the damp proof material.
Brick work being completed on the side of the building. This gives you a good look at the accent brick course.
Thursday, April 10, 2008
April 9, 2008
The Houndstooth continues to make good progress. The initial layer of asphalt has been completed in the back parking lot. At our meeting, we reviewed change orders that involve a protective bollard fence on the back of the property, canopy and roof drainage systems, an emergency roof drain and electrical wiring for the pool hall. It appears that all of these items will be implemented, though some of them are not necessarily required. They are all in the best interest of the building and property for the long run. The pictures below begin outside the front of the building. You can see that the block has been completed up to its total height. Studs and drywall will complete the walls to the top of the steel frame, and, of course, brick will be on the outside.
This crane is laying steel on top of the block wall after concrete has been pumped into the cavities of the block.
This crane is laying steel on top of the block wall after concrete has been pumped into the cavities of the block.Thursday, April 3, 2008
April 2, 2008 Site Meeting
The block work progress continues on the Houndstooth. The block does not go up to the top of the building. Metal studs and drywall will go on top of the block wall to complete the walls up to the metal frame. You can see the final heighth of the of the block in the second picture below. Scott, with K&A, says that the project is still about two weeks behind due to the site work that had to be done in the beginning. He believes that this lost time should be picked up by May. The project should be back on schedule at that time. Roof joists will be in by the middle of April.
This is a picture of the bar area. You can see the center counter stand in the middle.
Wednesday, March 26, 2008
March 26, 2008 Site Meeting
Subscribe to:
Posts (Atom)









